Tonawanda Creek at West Phalinger Remediation

Share |


Tonawanda Creek at West Phalinger Remediation
Project Details
Location: Clarence, New York
Client: Greenman-Pedersen, Inc. for Erie County Department of Public Works
Client Contact: Mr. Glenn Blake, 716-633-4844

Project Gallery

  • Photo 1
  • Photo 2
  • Photo 3
  • Photo 4
  • Photo 5
  • Photo 6
  • Photo 7
  • Photo 8
  • Photo 9
  • Photo 10
  • Phtoto 11
  • Photo 12
  • Photo 13

A slope failure along Tonawanda Creek damaged a portion of Tonawanda Creek Road between Transit Road and Westphalinger Road in the Town of Clarence. A section of Tonawanda Creek Road, approximately 250 feet long dropped about 10 feet and pushed soil into Tonawanda Creek. Subsurface explorations indicated that a thick deposit of soft clay was beneath the road.

MMCE developed design recommendations for remediating the soft clay conditions. Mixing dry cement with the soft clay soils to increase the strength and decrease the compressibility of the soft clay deposit was the selected remediation. MMCE completed stability analysis to determine the amount of improvement that was required to support the reconstructed roadway. Based on the stability analysis, MMCE developed design plans showing the extent of the dry soil mixing improvements. MMCE provided construction monitoring services throughout the project.  The project was completed in the winter and early spring of 2009.  





Related Documents

Tonawanda Creek at West Phalinger Remediation Project Description - This document contains information on this project