Campbell Boulevard Bridge Demolition
McMahon & Mann designed temporary footings to support two cranes that Oakgrove Construction, Inc. used during the Campbell Boulevard bridge demolition over Tonawanda Creek. The footing design considered the weight of the cranes, the weight of the bridge truss and the various crane positions that Oakgrove would use when lifting the truss. The position of the crane on the creek bank was determined by the crane’s lifting capacity and placed the footings at the top of the banks.